Below is an update from RMC on the progress as of 2/2. Items completed this week: Unit 124 drywall hung and taped on 2/1 Expected to complete texture and painting on 2/2. Will update if this changes. Unit 36 trim installed around the closet. Painter to return to touch up paint on the wall. Storage...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 1/26. Items completed this week: Roofing leak repairs completed at lodge, unit 124 & 36. Mitigation team removed cleanup equipment from 124 & 36 on 1/25. Items scheduled for next week: Drywall repairs in unit 124 scheduled for 1/31 and 2/1....Read More
Below is an update from RMC on the progress at Carnelian Woods as of 1/19. RMC was finally able to reach the manufacturer of the metal roofing material. They said the product is made in Sacramento and made to order so there should be no problem meeting our needs when ready. RMC will have more...Read More
The lodge and hot tub hours have been expanded for the holiday season, but note that they are closed on Christmas Day and on New Year’s Day. Hours adjust again on January 2. See the website for specifics.Read More
Below is an update from RMC on the progress at Carnelian Woods. Items completed this week: Remainder of upper buildings painted where siding was replaced. Unit 126 window trim repaired. Looks like we found the roofing material manufacturer, or at least a material almost identical. Spec sheet from the manufacturer looks correct. We are awaiting color...Read More
Below is an update from RMC on the progress at Carnelian Woods: Items completed this week: Unit 3 trim repaired and sealed. Unit 42 chimney sealed and vent pipe installed (by Don’s team). Final metal roofing will be installed once we have the permit and underlayment to install. Siding was installed and the chimney is...Read More
There has understandably been a lot of concern about completing the repairs to our units and ensuring the roofs don’t leak as winter weather starts. The insurance is covering all the damage to the units on a time and materials basis, so our primary contractor, Restoration Management Company (RMC), has every incentive to make sure...Read More
RMC continues to make substantial progress on repairing siding on our units. Here is their update from Friday, November 17, 2023: Completed this week: Unit 49 – we were made aware that the wall was damaged in this unit. Upon inspection we removed the siding and drywall, straightened out the wall, insulated both sides, hung...Read More
RMC continues to make substantial progress on repairing siding on our units. Here is their update from Friday, November 10, 2023: Items completed this week: Siding repairs completed up to unit 120. Unit 42 chimney resealed and covered while waiting for permit. More on this below. Painter to begin painting 11/11. Roofer inspected the remaining...Read More
Thank you all for your patience as we work our way through the repairs from last winter. As you probably know, more than half of our 118 units were damaged by the storms. Carnelian Woods is working with Restoration Management Company (RMC) to repair the portion of our units that is the HOA’s responsibility (covered...Read More