Below is an update from RMC on the progress at Carnelian Woods as of 8/30. Roofing crews are continuing with roofing. It is taking a little longer than expected. They plan to complete the bottom buildings by Wednesday next week, then move to the top section. The roofer will work through 9/7 and then have...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 8/9. Roofer returning to complete the remaining work on 8/12. They will address unit 52 leak first.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 8/2. Roofers have been continuing with the roof installation. Roofers will be off unit the 12th as both foreman are on vacation. We will pickup on the 12th and take about another week to week and a half to complete the roofing. Engineer...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 7/26 Roofers are continuing with roofing repairs. They have about 2-3 weeks remaining to complete everything. Window installed in unit 133 and drywall/paint repairs completed. No interior paint per the scope of work. All windows on the scope of work are...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 7/19. Window for unit 133 arrived on Thursday 7/18 and is stored in our storage bin. Scheduled to install with the client on Wednesday 7/24. Roofer will return on Tuesday 7/23 to begin installation of roofing materials. This process will continue...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 6/28. Roofers are continuing to remove affected roofing and install underlayment. They will continue until completed, expected to be through the next week. The window for unit 133 is still on schedule to arrive around 7/17.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 6/21. The roofer will be onsite Monday working throughout the property for one to two weeks to continue with the demolition and prepare for the roofing material arriving. Roofing panels are set to begin arriving in the next few weeks. The...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 6/7. All windows installed except for unit 133, and any affected siding and drywall repaired. Siding has been painted but drywall will not be painted as the insurance policy does not cover interior paint. Received a message from the window supplier...Read More