Below is an update from RMC on the progress at Carnelian Woods as of 5/15/25. All units are completed, final paint and permits are signed off. Crew is walking with the office to sign off. Chimney for unit 42 is signed off by the city and completed. All of the repair work should not be...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/9/25. Roofing completed on unit 42. Remaining siding and painting will be completed next week. Painters will complete the remainder of work on all decks next week. Job is expected to be completed by the end of next week.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/2/25. All structural work is completed and ready for painting. Chimney extension completed on unit 42. Roofer will arrive first part of next week to complete the top of the chimney. We have tarped and sealed it for now until the...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 4/25/25. All units passed framing inspection today. This includes all framing, hardware, attachments and posts. We will begin putting the decks back together over the weekend, weather permitting. Expect to complete several units this week, and the remaining the following week....Read More
Below is an update from RMC on the progress at Carnelian Woods as of 4/18/25. The primary remaining task is balcony repairs. Began demolition on units and are waiting for engineering details for the attachment of hardware. We moved forward on additional units because they needed to be opened up to see the attachment detail,...Read More
The pool has now unfrozen and staff will being preparing it to open. Assuming no extensive damage to be repaired, the pool is expected to open the Friday before Memorial Day, May 23. The staff will do their best to repair any damage to make the opening date, but many issues are not in their...Read More
Ramon Manzano of North Tahoe Protection District re-inspect the failing areas of Carnelian Woods and cleared the STR permits for this year. There are areas on the north side of units 143 and the south side of unit 147 that have large fuel loads that need some separation and will be reinspected in the next...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 9/13. Roofing repairs are completed! Roofers are awaiting a dumpster delivery to get the remainder of the debris removed off site. RMC is scheduling for the storage container and restroom to be picked up. RMC is awaiting plans on the balconies...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 9/6. Last update was reported that the roofer would be taking a break, but they are going to stay on site for the next week to attempt to complete the remaining roofing. Once the roofer is complete the storage bin will...Read More
North Tahoe PUD plans to replace the water service laterals to Carnelian Woods–Units 33 to 46. Construction will begin after Labor Day and be substantially complete by October 15th with site clean-up work likely continuing until the end of October. The site is a very challenging area to dig, with a lot of rock, so they are...Read More