Below is an update from RMC on the progress at Carnelian Woods as of 6/21. The roofer will be onsite Monday working throughout the property for one to two weeks to continue with the demolition and prepare for the roofing material arriving. Roofing panels are set to begin arriving in the next few weeks. The...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 6/7. All windows installed except for unit 133, and any affected siding and drywall repaired. Siding has been painted but drywall will not be painted as the insurance policy does not cover interior paint. Received a message from the window supplier...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/24. Window replacement will start on three units on Tuesday, May 28. If you know you have a window repair and have not heard from the office, please contact Janessa at the Carnelian Woods office to schedule. Crews will be working...Read More
Greetings Rakers, It’s that time again when we gather to remove flammable debris and chat with other Carnelian Woods homeowners and friends! Grab your hats and sunglasses, slather on some sunscreen and prepare to sweat and get dusty! Friday, July 12th at 0900 (ish) at the Upper Units Water, rakes and gloves provided. Pizza for lunch...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/17. Good news, RMC is going to have crews on site starting Tuesday, May 28th to start on the window replacements and some of the remaining exterior work. They will need access to ten of the units. The office will contact...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/10. RMC is working with the contractors to have a date to start the window installs by next week. The roofing manufacturer has not provided a delivery date yet, just that the material is ordered and awaiting production. They plan to...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/3. RMC has ordered the coils of roofing material. The roofing manufacturer needs exact measurements of the material sizing that is being replaced. RMC’s plan is to begin removing the damaged roofing material soon, then install the underlayment and seal the...Read More
Linchpin Engineering staff will be on the Carnelian Woods property beginning this Thursday, May 2, at 9 AM, to conduct inspections of the balconies as required by California Civil Code 5551. There will likely be one or more additional days scheduled in the future to complete the project. The first inspections are required before January...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 4/26. The roofing materials have been ordered. We do not have an ETA yet, but RMC will be checking with them weekly and report back as soon as they have a timeline. RMC is working on a timeline to start all...Read More
Homeowners have been contacting the office looking for information on solutions to the issue of now needed an egress window in their lofts to claim it as a bedroom for short term rentals. Jack Venable, the Architecture Review Committee Chair who will process any applications for changes to your unit, spent much of his career...Read More