Western Bat Specialists will be out October 23-24 to install bat exclusion devices. Bats gaining entry to external structure at unit 50, 53, 55, and 57. Bat proofing at units 13, 14, 15, 16, 17, 19, 20, 30, 63, 64, 122, 127, 132 and 143. Read More
The Best Stove and Chimney Service will be out to service the units that have wood-burning fireplaces, as required by the CC&Rs. Tuesday, November 18: inspections Wednesday, November 19: sweeps Thursday, November 20: sweeps finish.Read More
Western Bat Specialists will be out October 20-22 to install bat exclusion devices. Bats gaining entry to external structure at unit 50, 53, 55, and 57. Bat proofing at units 13, 14, 15, 16, 17, 19, 20, 30, 63, 64, 122, 127, 132 and 143. Read More
Tree Mechanic will be out removing some dangerous dead/dying trees near the units: in front of unit 124, between units 52 and 53, and behind unit 25. The work might be delayed due to weather. Read More
Due to the tremendous increase in our insurance costs, per Davis Stirling law, the regular assessment for 2025/26 will need to be approved by a vote of the members. Bottom line, this ballot is to approve a 1.78% increase over the quarterly dues payment in the July quarter to $3569 from $3507. The $438.00/quarter special...Read More
Greetings Rakers, We hope you can join us for the annual Rake-Off event this SUNDAY, JUNE 29, at 9am, in the upper lots near Units 120-135. It’s time again to do some raking to remove flammable debris and chat with other Carnelian Woods homeowners and friends! Grab your hats and sunglasses, bring your favorite water bottles (full of delicious...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/15/25. All units are completed, final paint and permits are signed off. Crew is walking with the office to sign off. Chimney for unit 42 is signed off by the city and completed. All of the repair work should not be...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/9/25. Roofing completed on unit 42. Remaining siding and painting will be completed next week. Painters will complete the remainder of work on all decks next week. Job is expected to be completed by the end of next week.Read More
Below is an update from RMC on the progress at Carnelian Woods as of 5/2/25. All structural work is completed and ready for painting. Chimney extension completed on unit 42. Roofer will arrive first part of next week to complete the top of the chimney. We have tarped and sealed it for now until the...Read More
Below is an update from RMC on the progress at Carnelian Woods as of 4/25/25. All units passed framing inspection today. This includes all framing, hardware, attachments and posts. We will begin putting the decks back together over the weekend, weather permitting. Expect to complete several units this week, and the remaining the following week....Read More