Below is an update from RMC on the progress at Carnelian Woods as of 4/25/25.

  • All units passed framing inspection today. This includes all framing, hardware, attachments and posts.
  • We will begin putting the decks back together over the weekend, weather permitting. Expect to complete several units this week, and the remaining the following week. Once completed we will need to call for final inspection with the county.
  • The inspector required specialty coated hangers and other materials that were not on the plans. These items were special orders and have mostly been received. We are waiting for a couple more items to arrive, but nothing that will delay the project.
  • The engineer made some engineering changes due to the inspectors request for a few attachment areas. These areas were different than the engineer assumed once we opened up the areas and were able to see the actual framing in the walls. All is resolved, just cost us a few days of gathering engineering details, materials and specialty hardware.

Related Posts

#printfriendly #pf-src { display: none !important; } #printfriendly #pf-title { display: none !important; }